Resource type
Date created
2015-08
Authors/Contributors
Author: Adam Brooks
Abstract
The British Columbia (BC) Government introduced the Clean Energy Act in 2010. With the new legislation, BC Hydro has been mandated to be electricity self sufficient by 2016. BC Hydro may not have enough generation capacity to meet the regulatory requirement in time. This project explores three potential options for Teck’s Zinc Smelter to provide made-in-BC generation capacity to BC Hydro. After evaluating the options, this author recommends for Teck to make an offer to swap BC Hydro’s imports with Teck’s made-in-BC generation.
Document
Description
EMBA Project - Simon Fraser University
Copyright statement
Copyright is held by the author(s).
Scholarly level
Peer reviewed?
No
Language
English
Member of collection